Unfortunately, apples are currently being charged with oranges as part of the overhead costs. It is possible to upload actual personnel costs. However, the personnel costs stored in the contract information are then distributed (among projects, absences, etc.) and not the actual costs uploaded. The difference then ends up in overhead costs (“Debit to Posted Difference”). In my opinion, this distorts overhead costs enormously. Or am I wrong about that?
How can you fix that? That would be super important... otherwise the overhead costs would be distorted far too much, as the difference (which is always there) is simply apportioned as a lump sum.
·